Lochinvar Development: Every Project, Address and Status

Lochinvar development has now moved from paper to bulldozers. We tracked 8 live projects in and around the Lochinvar Urban Release Area, which together cover more than 1,200 lots with a DA number attached, plus 415 manufactured home sites still in assessment. The newest news came in September 2026, since Maitland councillors voted 12-0 for a 139-lot estate behind St Joseph’s College. Then in August, a 350-student private school went to the regional planning panel. And the town centre finally has a builder and a 2027 finish date. So here is every project, its address and its status, as well as the roads and schools behind it.

This article was produced and reviewed by the Australia Develops editorial team. See our Editorial Policy for sourcing standards and methodology.

Where is Lochinvar?

Lochinvar is a Hunter Valley village in Maitland City Council (postcode 2321), about 40 km north-west of the Newcastle CBD and about 132 km north of the Sydney CBD in a straight line, with Maitland about 10 km to the east. It sits on the New England Highway, while Lochinvar station on the Hunter Line lies about 2 km south of the old village (the name comes from a Scottish loch).

Map of the Lower Hunter showing Lochinvar NSW 2321 west of Maitland and north-west of Newcastle
Lochinvar sits on the New England Highway west of Maitland, so it’s inland from Newcastle. Imagery: Google Maps.

Lochinvar Development — The Pipeline

First, the background. Initially, the state rezoned about 650 hectares here in October 2011 for “up to 5,000 dwellings”, according to the NSW Planning Portal record (PP-2021-733). Yet growth was slow for years. At the 2021 Census, the suburb still had only 1,095 residents and 439 private dwellings. So most of what follows is new, and much of it is happening now.

NSW Planning Portal record for the Lochinvar Investigation Area PP-2021-733 showing 650 hectares rezoned for up to 5,000 dwellings
The 2011 rezoning that first created the Lochinvar Urban Release Area. Source: NSW Planning Portal.

The 8 Lochinvar development projects at a glance

The quickest way to see the scale is side by side. Below is every project we could tie to a development application, with the developer, the number of lots and where each one currently sits in the system.

#Project / addressDeveloperScaleStatus
1Kaludah estate, 134 and 146 Station LaneMcCloy Group353 lots in DA/2022/511; about 780 homesites marketed2021 panel refusal; redesigned estate now in civil works
2Wyndella Road estate, 2 Cantwell Rd and 25, 39 and 55 Wyndella RdLochinvar Developments Pty Ltd258 lots, 14 stagesApproved August 2025
3Diocese estate, 20 and 20A Cantwell Rd and 60 New England HwyCatholic Diocese of Maitland-Newcastle139 lots; $21.42mApproved 15 Sep 2026
4Station Lane estate, 213 and 215 Station LaneNot named in reports140 lotsApproved February 2025
5Lochinvar Ridge, 70 Christopher RoadUrban Land Housing312 lots approved 2023; Stages 16 to 21 lodged 2026Selling; new DA under assessment
6Town centre and Lochinvar Shopping Village, Springfield DriveGWHSupermarket, bottle shop, shops, pub; $29.3mApproved Dec 2024; finish end 2027
7St Philip’s Christian College, 52 Wyndella RoadSt Philip’s Christian Education Foundation350 students; $19.7mUnder assessment (PPSHCC-431)
8Manufactured home estates, 34 Wyndella Rd and 1064 New England HwyCommercial 7; applicant for 1064 not confirmed209 and 206 sitesCourt appeal; amended DA re-notified 2026

Read down that table and the pattern is clear: this is a subdivision pipeline rather than an apartment one, with most of the volume in a handful of large estates and the town centre still the piece everything else waits on. The headline numbers are worth pulling out on their own.

8
live projects in the Lochinvar pipeline
1,200+
lots in subdivisions with a DA number
350
students in the proposed St Philip’s school
$29.3m
shopping village approved December 2024

Where the Lochinvar Development Projects Sit

Those projects are easier to follow with the geography in front of you. Lochinvar sits in a narrow band between the New England Highway and the rail line, and almost every estate here runs off Station Lane, Wyndella Road or Cantwell Road, so the overview below is the quickest way to place them.

Satellite view of the Lochinvar development area between the New England Highway and Lochinvar station
The general area: the release land between the New England Highway and the railway, such as Station Lane, Springfield Drive and Wyndella Road. General site, not a confirmed lot line. Imagery: Google Maps.

For a start, think of the release area as a wedge. The New England Highway forms the northern edge, while the Hunter Line runs along the south. Station Lane connects the two, so it carries Kaludah and the 140-lot estate near the station. Then to the west, Wyndella Road holds the 258-lot estate, the school site and one of the home estates. Next, Cantwell Road sits behind St Joseph’s College. Finally, Springfield Drive and Christopher Road form the new spine, with Lochinvar Ridge and the future town centre.

PROJECT 1 — About 780 homesites at Kaludah, 146 Station Lane

Status: Earlier 855-lot plan refused (Hunter and Central Coast Regional Planning Panel, 16 November 2021); redesigned estate now in civil works

Location: 146 Station Lane, Lochinvar NSW 2321, as well as 134 and 51 Station Lane. The developer is McCloy Group, which also built the neighbouring Hereford Hill estate. Its Kaludah website describes 101 hectares and “approximately 780 new homesites” averaging about 600 m², although a summary box on the same page says 708. So treat the total as a range for now.

Motor grader and roller shaping a new estate road through farmland, with drainage pipes stacked beside it
Civil works are the stage Kaludah is at now: roads, drainage and levels go in long before a single house does.

Why the panel refused the first plan

Of course, this land has a history. In December 2020, McCloy Project Management lodged DA/2020/1388 for a concept plan of 855 lots in 6 stages, with a capital value of $44,882,458. But the regional planning panel refused it unanimously on 16 November 2021. Its statement of reasons listed 15 grounds, such as poor lot layout, unacceptable vegetation loss, excess cut and fill, and traffic impacts. In addition, the panel found the developer hadn’t shown it could deliver the infrastructure, and it said the koala habitat policy still needed addressing.

NSW Planning Portal panel page for PPSHCC-64 DA/2020/1388 at 134 Station Lane Lochinvar showing the Refused determination outcome
The 2021 refusal of the 855-lot concept plan, which came before the redesign. Source: NSW Planning Portal, regional planning panels.

What came next on Station Lane

After that, McCloy came back with a smaller plan. Next, council exhibited DA/2022/511 for a staged subdivision of 353 residential lots, 5 public purpose lots, a new road and a local park on the same 3 Station Lane addresses. Then on 2 March 2023, the developer signed a state planning agreement for 134 Station Lane at $91,250 per hectare of net developable area. However, we couldn’t find the determination notice for DA/2022/511 itself. So we can’t give you its approval date.

Still, what we can confirm is on the ground. Currently, the Kaludah site says civil works have shut off public access. Its masterplan labels Stage 4A as the “Cork Release”. In 2026, council also exhibited DA/2026/434 for a sales office, landscaping and a driveway at 51 Station Lane. That’s normally a sign that lots are close to release, because builders want buyers on site early.

Google Maps satellite view of the Kaludah estate at 146 Station Lane, Lochinvar NSW 2321
The exact site: 146 Station Lane, Lochinvar NSW 2321, south of the New England Highway as you head towards Lochinvar station. Imagery: Google Maps.

PROJECT 2 — 258 lots at 39 Wyndella Road

Status: Approved (Maitland City Council, August 2025); modification lodged December 2025

Location: 39 Wyndella Road, Lochinvar NSW 2321, as well as 25 and 55 Wyndella Road and 2 Cantwell Road. The application is DA/2023/415, and the developer named on the state planning agreement is Lochinvar Developments Pty Ltd. In short, the site covers 22.54 hectares between the highway and Wyndella Road.

Councillors approved 258 lots over 14 stages at their August 2025 meeting, the Maitland Mercury reported. Lots range from 450 to 1,200 m², so there’s a mix of standard and larger blocks. The approval also includes 2 public reserves, a drainage reserve, and the widening of Wyndella Road with footpaths and a highway connection. As a result, about 0.94 hectares of native vegetation will go.

Kerb-laying machine extruding concrete kerb along a new subdivision road
Clearing, earthworks and kerbs are what a lot number actually looks like on the ground in the first year or two.

The planning agreement and road dedication

The parties then signed the state planning agreement (SVPA2023-56) on 26 September 2025. However, it describes “approximately 256 residential lots”, which is slightly lower than the council figure. Also, it requires the developer to dedicate 1,939 m² of land for widening Wyndella Road and to pay $101,578 per hectare of net developable area. Since then, ADW Johnson has lodged a modification (DA/2023/415/1) to change the road and drainage design of Wyndella Road. We found no decision on it yet.

NSW Planning Portal planning agreement for 39 Wyndella Road Lochinvar showing DA/2023/415, about 256 lots and $101,578 per hectare
The state planning agreement for the Wyndella Road estate, signed after the council approval. Source: NSW Planning Portal, planning agreements register.

The agreement sets out what the developer has to hand over. The satellite view shows the land it applies to, which is still paddock at this point.

Google Maps satellite view of the 258-lot estate at 39 Wyndella Road, Lochinvar NSW 2321
The exact site: 39 Wyndella Road, Lochinvar NSW 2321, the paddocks between Wyndella Road and Cantwell Road. General site, not a confirmed lot line. Imagery: Google Maps.

PROJECT 3 — 139 lots at 20 Cantwell Road, behind St Joseph’s

Status: Approved (Maitland City Council, 15 September 2026, 12-0)

Location: 20 Cantwell Road, Lochinvar NSW 2321, as well as 20A Cantwell Road and 60 New England Highway. The applicant is the Trustees of the Roman Catholic Church for the Diocese of Maitland-Newcastle, and the land sits behind St Joseph’s College. Council initially exhibited the plan as DA/2025/138.

In fact, this is the newest approval in the Lochinvar development pipeline. Initially, the Diocese sought 138 lots over 3 stages and expected to finish in 2026. But the final consent covers a 3-into-141 lot subdivision, which creates 139 residential lots from 450 to 869 m² on 16.6 hectares. Its estimated cost is $21.42 million, so councillors decided it rather than staff.

The heritage trees on Cantwell Road

Workers in high-visibility gear digging carefully beside mature pine trees in front of an old homestead
Mature trees are the sort of condition that reshapes a layout, because they have to be designed around rather than removed.

One change shaped the approval, though. In 2025, a resident raised concerns that widening Cantwell Road would harm 2 century-old hoop pines and a bunya pine near the state-listed Nowlands Lochinvar Coach House. So the design now widens the road on the eastern side only, and an arborist recommended hand digging near root zones. The 2026 finish date the Diocese hoped for now looks unlikely, since construction can only start after consent.

Google Maps satellite view of the Diocese estate site at 20 Cantwell Road, Lochinvar NSW 2321 behind St Joseph's College
The exact site: 20 Cantwell Road, Lochinvar NSW 2321, just north of St Joseph’s College. Imagery: Google Maps.

PROJECT 4 — 140 lots at 213 Station Lane, by the station

Status: Approved (Maitland City Council, 11 February 2025, unanimous)

Location: 213 Station Lane, Lochinvar NSW 2321, as well as 215 Station Lane. Councillors gave consent for a 140-lot subdivision with a public reserve and 2 detention basins, the Maitland Mercury reported. Also, ward 4 councillor Don Ferris pointed out it sits right by Lochinvar station.

But reports didn’t name the developer or the DA number. Council had earlier re-notified DA/2021/473 for 164 lots at 213 Station Lane, so this is probably the same file, cut down. Still, we couldn’t confirm that link on an official page. For buyers, then, the appeal is plain: it’s the closest new estate to a train platform in the whole release area.

PROJECT 5 — Lochinvar Ridge stages at 70 Christopher Road

Status: 312-lot extension approved (Maitland City Council, May 2023); Stages 16 to 21 lodged as DA/2026/170

Location: 70 Christopher Road, Lochinvar NSW 2321, as well as 799 New England Highway. Urban Land Housing runs Lochinvar Ridge, and its managing director is Christopher Lowry. So far, the developer has marketed the estate as more than 650 lots in total.

In May 2023, councillors unanimously approved an extension of 312 blocks from 450 to 1,406 m² in 10 stages. Council had exhibited it as DA/2021/1460 for 307 lots, and a later modification followed in December 2024. The consent also includes a local park, a kiosk, 2 detention basins and an upgrade of the highway intersection at Springfield Drive and Sanctuary Drive. Then in April 2026, council published documents for DA/2026/170, covering Stages 16 to 21 off Cowhill Road. The lot count for that new application was not available, so it is left out of the totals.

Other Lochinvar development approvals nearby

Of course, there are smaller files too. For example, in June 2024 councillors approved 90 lots off Windermere Road, in the north-west corner of the release area, plus a residue lot of just over 40 hectares. In addition, infill DAs keep arriving, such as 8 lots at 5 Christopher Road and 11 lots at 21 St Helena Close.

PROJECT 6 — Town centre and shopping village on Springfield Drive

Status: Town centre rezoning made (8 July 2021); shopping village approved (Maitland City Council, 10 December 2024); builder targets end 2027

Location: 93 Springfield Drive, Lochinvar NSW 2321, which is the address used in council reporting. However, the builder GWH lists the project at 30 Christopher Road, so the street address may be changing as roads are named. Either way, the rezoned town centre land sits at the corner of Christopher Road and Station Lane.

The rezoning behind the town centre

The land use came first. In this case, planning proposal PP-2021-507 rezoned part of Lot 310 DP1034974 from residential to a local centre zone. Its stated aim, in other words, was “a new town centre within the Lochinvar urban release area”. It went on exhibition from 12 October to 9 November 2020, and the amendment was published on 8 July 2021, according to the Planning Portal.

NSW Planning Portal record PP-2021-507 for a new town centre within the Lochinvar urban release area, marked Approved
The 2021 rezoning that now allows the Lochinvar town centre. Source: NSW Planning Portal.

What’s approved in the shopping village

Council approved the $29,255,928 Lochinvar Shopping Village on 10 December 2024. It comes in 3 stages, and stage 1 is a supermarket and bottle shop. Next comes a commercial building, and stage 3 is a pub with dining, gaming and an outdoor terrace. In total, there are also 319 car spaces. Later, the Maitland Mercury described the supermarket as a Woolworths in May 2026. By contrast, GWH’s own page only says “full-line national supermarket”, so we’d treat the brand as likely but unconfirmed.

Currently, GWH’s project page lists construction starting in 2026 and completion at the end of 2027. It also mentions a 130-place childcare centre next door, due in 2026. Under the consent, of course, the approval lapses after 5 years if work doesn’t start.

PROJECT 7 — A 350-student school at 52 Wyndella Road

Status: Under assessment (Hunter and Central Coast Regional Planning Panel, PPSHCC-431, referred 11 August 2026)

Location: 52 Wyndella Road, Lochinvar NSW 2321, which is a 10.71-hectare grazing property about 1.5 km north-west of the village centre. The applicant is the St Philip’s Christian Education Foundation, which already runs campuses in Newcastle, Cessnock, Gosford and Port Stephens. The proposed school, in this case, is St Philip’s Christian College Maitland.

The panel record shows DA/2026/560, lodged on 3 August 2026, with a capital investment value of $19,742,422. In particular, it covers a 2-storey junior school building, a single-storey modular building, a canteen and ancillary works. According to the Newcastle Herald, the plan caps enrolments at Year 10 for now and provides 350 places. It also includes a sports field, a hardstand court, bus bays, a kiss-and-drop zone and a right-turn bay on Wyndella Road.

NSW Planning Portal panel page for PPSHCC-431 DA/2026/560 at 52 Wyndella Road Lochinvar, under assessment with a $19,742,422 CIV
The school application is still under assessment by the regional planning panel. Source: NSW Planning Portal, regional planning panels.

Eventually, the foundation wants to grow the campus to about 1,200 students from K to 12. But this DA doesn’t seek approval for that. So any high school years beyond Year 10 would need a separate application later.

Google Maps satellite view of the proposed St Philip's school site at 52 Wyndella Road, Lochinvar NSW 2321
The exact site: 52 Wyndella Road, Lochinvar NSW 2321, east of Wyndella Road. General site, not a confirmed lot line. Imagery: Google Maps.

PROJECT 8 — 415 manufactured home sites on 2 sites

Status: 34 Wyndella Road in the Land and Environment Court (deemed refusal, amended plans re-notified May 2025); 1064 New England Highway amended and re-notified April 2026

Currently, these are the most contested Lochinvar development files. Both are land-lease communities, where residents own the home but rent the site.

34 Wyndella Road: 209 sites

Location: 34 Wyndella Road, Lochinvar NSW 2321. DA/2024/116 seeks demolition and a manufactured home estate of 209 dwelling sites with communal facilities in 7 stages. Also, the applicant is Commercial 7. Council didn’t decide within 60 days, so the applicant took a deemed refusal to the Land and Environment Court in 2024. Council said it would oppose the appeal, because it argued that homes built on site breach the rule that manufactured homes must be made off site. Also, all 85 submissions objected or raised concerns.

Then in May 2025, council re-notified amended plans and an addendum environmental report. That usually means the parties are negotiating in court, although not always. However, we couldn’t find a published judgment or consent. So the next step is a court outcome, and that date isn’t public.

1064 New England Highway: 206 sites

Location: 1064 New England Highway, Lochinvar NSW 2321. DA/2024/823 was lodged in October 2024 for a 206-lot manufactured home estate, community facilities, a display suite and demolition. Later, the applicant filed an amended application dated 5 March 2026. Council then re-notified it in April 2026 with a new environmental statement, a social impact assessment and an accessibility review. It still remains under assessment, and we couldn’t confirm the final site count after the amendment.

Google Maps satellite view of the proposed manufactured home estate at 1064 New England Highway, Lochinvar NSW 2321
The exact site: 1064 New England Highway, Lochinvar NSW 2321, on the northern side of the highway at the western edge of the village. General site, not a confirmed lot line. Imagery: Google Maps.

The Infrastructure Behind Lochinvar Development

Infrastructure in Lochinvar comes from 3 sources: the state, the council and the developers themselves. So here’s what is built, funded or simply planned.

Roads: the highway lights and the new Springfield Drive link

  • New England Highway and Wyndella Road (done). First, traffic lights switched on in October 2019 after a $11.5 million NSW Government job. It also widened the highway to 2 lanes each way at Wyndella Road and added turning lanes. The Housing Acceleration Fund paid for it, and Transport for NSW lists it as completed.
  • Springfield Drive link (done). Built by Urban Land Housing, Hunter Land (Lochinvar Downs) and McCloy Group, it opened in June 2026. Also, it ties the town centre to the estates and the station. Mayor Philip Penfold said it now allows 52 more lots in the short term.
  • Highway at Springfield Drive and Sanctuary Drive (developer condition). This upgrade is part of the 2023 Lochinvar Ridge consent, but we found no completion date.
  • Wyndella Road widening (developer condition). It comes with the 258-lot estate, such as 1,939 m² of dedicated land.
NSW Planning Portal planning agreement for 134 Station Lane Lochinvar with McCloy Project Management at $91,250 per hectare, executed 2 March 2023
Each estate also pays a per-hectare levy toward state infrastructure. Source: NSW Planning Portal, planning agreements register.

Rail, schools and health

Lochinvar station is on the Hunter Line between Maitland and Singleton. However, we found no funded station upgrade, extra parking or service increase announced for it. On schools, Lochinvar already has Lochinvar Public School, St Patrick’s Primary and St Joseph’s College. The Diocese says its investment at Lochinvar and Chisholm creates room for 2,000 students across those schools. Still, the Department of Education hasn’t announced a new public school for Lochinvar. Its nearby new builds are in Huntlee and Chisholm instead. For hospital care, residents currently use the Maitland Hospital at Metford.

Local services, as a result, are following the rooftops. For example, council has exhibited a medical centre at 106 New England Highway (DA/2025/368) and childcare centres at 1 to 5 Station Lane (DA/2025/36) and 127 New England Highway (DA/2025/796, 108 children). However, we haven’t confirmed decisions on those 3.

DONE
URA rezoning (Oct 2011); highway lights at Wyndella Rd (Oct 2019); town centre rezoning (Jul 2021); shopping village approved (Dec 2024); 258 lots approved (Aug 2025); Springfield Drive link (Jun 2026); 139 lots approved (Sep 2026)
NEXT
St Philip’s school panel decision; Kaludah Stage 4A release; shopping village build, finish end 2027
UNCONFIRMED
Manufactured home estate outcomes; Lochinvar Ridge Stages 16 to 21; new public school; station upgrade

What’s Next to Watch in Lochinvar Development

The next 12 to 18 months should bring several visible changes. So here’s what we’re watching.

  • The next step for St Philip’s is the regional planning panel’s decision on PPSHCC-431. No meeting date is listed yet, so watch the panel page.
  • Watch for GWH starting the shopping village on Springfield Drive. Then stage 1, the supermarket, is the part locals will feel first.
  • Kaludah’s Stage 4A “Cork Release” is the next McCloy release, and the sales office DA at 51 Station Lane is the signal to look for.
  • The Diocese can now move to construction certificates for the 139 lots on Cantwell Road. Early civil works would be the next sign.
  • Council’s decision on Lochinvar Ridge Stages 16 to 21 (DA/2026/170) will add the next run of lots off Cowhill Road.
  • Watch for a court outcome at 34 Wyndella Road and a council decision at 1064 New England Highway. Both dates are still unknown.
  • For schools and rail, the next step would be a state funding announcement. None is dated yet, so the state budget is the place to look.

Lochinvar Development Project Status and Delivery Timing

ProjectHomesStageDecision makerExpected timing
Kaludah, Station Lane353 in DA/2022/511; about 780 marketedCivil works; sales office DA lodgedMaitland City Council (2021 refusal by regional panel)Stage 4A next; date not stated
Wyndella Road estate258Approved; modification lodgedMaitland City Council14 stages; dates not stated
Diocese estate, Cantwell Road139Approved Sep 2026Maitland City CouncilStart not announced
213 and 215 Station Lane140Approved Feb 2025Maitland City CouncilNot stated
Lochinvar Ridge extension312, plus Stages 16 to 21Selling; new DA under assessmentMaitland City Council10 stages; ongoing
Shopping village0Approved Dec 2024Maitland City CouncilBuild from 2026; finish end 2027
St Philip’s school0 (350 students)Under assessmentHunter and Central Coast Regional Planning PanelNot stated
Manufactured home estates209 and 206 sitesCourt appeal; under assessmentLand and Environment Court; Maitland City CouncilNot stated

Our Take on Lochinvar Development

Lochinvar development took 15 years to get going, but the pieces now fit. The highway lights, the Springfield Drive link and the town centre zoning are done. In addition, 5 big estates have consents, and a supermarket has a builder. In fact, that’s more concrete than many growth suburbs can show. Also, the 2021 refusal on Station Lane shows the panel will push back on poor layouts, which protects buyers in the long run.

The gap, however, is public infrastructure. There’s no new public school, no funded station upgrade and no dated highway plan beyond the developer works. So if you’re buying here, we’d buy for the land, the price and the train line that already exists. Instead, we wouldn’t count on state projects nobody has funded. Compared with Huntlee up the road, which has a public school precinct under construction, Lochinvar is behind on schools but ahead on rail access.

Questions locals are asking

When will Lochinvar get a Woolworths?

The approved shopping village includes a full-line supermarket, and the Maitland Mercury reported it as a Woolworths. Currently, GWH lists completion at the end of 2027. But the brand isn’t on any official page we could find, so treat it as likely rather than certain.

Is a new public school coming to Lochinvar?

Not yet. So far, the Department of Education hasn’t announced one. The only new school proposal is St Philip’s Christian College at 52 Wyndella Road, which is a private school and still under assessment by the regional panel.

How many homes will Lochinvar eventually have?

Initially, the 2011 rezoning allowed “up to 5,000 dwellings” across about 650 hectares. Right now, the estates with DA numbers add up to more than 1,200 lots, which is roughly a quarter of that. If you’re working out costs on a block here, check NSW stamp duty and the 5% deposit scheme caps first. It’s also worth reading up on house construction costs before you pick a builder.

What happened to the 855-lot Station Lane plan?

The regional planning panel refused it in November 2021 on 15 grounds, including layout, vegetation loss and traffic. Then McCloy lodged a smaller 353-lot plan, and that land is now the Kaludah estate. Lochinvar is one small piece of the national 1.2 million homes target, and greenfield estates like this are where much of the Hunter’s share comes from.

This article is general information based on NSW Planning Portal records, Maitland City Council notices, Transport for NSW and local news reports available at publication. It isn’t financial advice. Approvals, lot numbers and timelines can change, so check current details with the developer and Maitland City Council before you buy.