Vineyard development is finally moving after years of slow starts. For this guide, we tracked 7 projects in and around the suburb. They range from a Stage 1 precinct with room for up to 2,300 homes to 158 townhouses on Windsor Road. The biggest news, though, is a road. Then in July 2026 the NSW Government added $250 million to the Bandon Road upgrade. So the level crossing at Vineyard station will go. On top of that, Vineyard Public School is moving to a new campus at Grantham Farm. Here is every project, its address and its status, with the infrastructure that’s funded and the parts still waiting.
This article was produced and reviewed by the Australia Develops editorial team. See our Editorial Policy for sourcing standards and methodology.
Where is Vineyard?

Vineyard (postcode 2765) sits mostly in Hawkesbury City Council, with some Windsor Road addresses in Blacktown City, about 41 km north-west of the Sydney CBD and 23 km from Parramatta in a straight line. It’s also about 6 km south-east of Windsor, with its own station on the Richmond branch of the T1 line, and it’s a Sydney suburb, not a wine region.
Vineyard Development — The Pipeline
First, some context. Vineyard is a precinct of the North West Growth Area, and the state split it in 2 parts. Then the state rezoned Stage 1 for housing in December 2017. Stage 2, the larger rural balance of the precinct, still has no rezoning date. At the 2021 Census, the whole suburb had just 1,143 residents and 535 private dwellings, according to the ABS QuickStats. So nearly all of the change is still ahead. Most applications are subdivisions along Commercial Road and Chapman Road, while the biggest single building approval sits on Windsor Road.
The 7 Vineyard development projects at a glance
| # | Project / address | Developer | Scale | Status |
|---|---|---|---|---|
| 1 | Vineyard Precinct Stage 1 rezoning, around Commercial Road and Chapman Road | State-led rezoning; about 270 landholders | Up to 2,300 homes; 27 ha open space; school site | Rezoned 15 Dec 2017; still building out |
| 2 | Townhouses, 1578 to 1586 Windsor Road | Universal Property Group | 158 two-storey dwellings; $41.7m | Refused 2023, then approved by court 12 Nov 2024 |
| 3 | Concept subdivision, 238 Commercial Road | Not named in the public listing | 69 lots and 3 residue lots in stages | Approved (DA0552/19); MOD0062/26 now lodged |
| 4 | Subdivision, 260 Commercial Road | Not named in the public listing | 29 lots and 2 residue lots | Deferred commencement consent (DA0199/25); MOD0026/26 now lodged |
| 5 | Subdivision, 283 Commercial Road | Not named in the public listing | 15 lots and 2 residue lots | Lodged; no decision found yet |
| 6 | Depot and warehouse uses, 172 Commercial Road | Mecone for the landowner | Up to 8,000 m² proposed, such as warehouses | LEP change published 6 Dec 2024; DA still to come |
| 7 | Vineyard Precinct Stage 2, the balance of the precinct | NSW Government | Possible employment land | Still deferred; no timeframe |
Read down that table and the split becomes obvious. Two of the seven entries are state-led rezonings that set the rules for the whole precinct, while the other five are the development applications that actually turn paddocks into lots, townhouses and sheds. The figures below pull out the numbers that matter most across all seven.
Where the Vineyard Development Projects Sit
Currently, most Vineyard development happens in a tight band. Commercial Road is the spine, so 4 of the 7 projects have a Commercial Road address. Then Chapman Road crosses it. Stage 1 housing sits on one side, while the 172 Commercial Road site and Stage 2 sit on the other. Next, Windsor Road runs along the eastern edge, where the townhouse site sits at numbers 1578 to 1586. Also, Vineyard station and the Bandon Road level crossing sit beside Riverstone Parade. Finally, the Killarney Chain of Ponds creek winds through Stage 1. That’s also where most of the new parkland goes.

PROJECT 1 — Up to 2,300 homes in the Vineyard Precinct Stage 1 rezoning
Status: Rezoned (State Environmental Planning Policy amendment published 15 December 2017); subdivision and home building under way
Location: the Stage 1 area around Commercial Road and Chapman Road, Vineyard NSW 2765. This is a state-led rezoning, not a single developer’s project, so delivery is piecemeal. The planning instrument is the Hawkesbury Growth Centres Precinct Plan. The state published it on 15 December 2017 as an amendment to the Growth Centres SEPP. Since there are about 270 landholders in the wider precinct, delivery depends on each owner deciding to sell or subdivide.
What the Stage 1 rezoning allows

The NSW Planning precinct page sums it up as up to 2,300 new homes and a proposed primary school. It also lists a village centre and around 27 hectares of open space along the creek. Then the November 2017 finalisation report gives the detail. For instance, Stage 1 covers 230.2 hectares, including 160.6 hectares of residential land. Then it caps density at 18 homes per hectare in the R2 zone and 30 in the R3 zone. In fact, Vineyard was one of the first precincts with a housing cap, because of flood evacuation limits.
Lots, flooding and the village centre
About a third of the precinct sits under the 1 in 100 year flood level, according to the finalisation report. So no new homes can go below the flood planning level. Also, the most flood-affected land has a 20,000 m² minimum lot size. Still, the village centre is small: 0.8 hectares, or 1.4 hectares with the mixed use strip. Still, the council’s Vineyard Precinct contributions plan from 23 February 2021 allows for up to 5,500 m² of retail. That plan also projects 2,565 dwellings, a bit above the 2,300 headline, because it counts the whole charging area.

Currently, new streets and houses are filling in. For example, new homes and pools on streets such as Magic Street, Firetail Street and Oroya Crescent keep turning up on PlanningAlerts. However, we couldn’t find any lodged application for the village centre or the supermarket the state plan mentions. So that remains the missing piece for Stage 1.
PROJECT 2 — 158 townhouses at 1578 to 1586 Windsor Road
Status: Approved by the Land and Environment Court (12 November 2024) after a panel refusal; road width change approved 7 July 2026
Location: 1578, 1580, 1584 and 1586 Windsor Road, Vineyard NSW 2765. This site falls under Blacktown City Council, not Hawkesbury, which is why the Central City panel handled it. Also, the applicant was Universal Property Group Pty Ltd. The application number is SPP-23-00037 and the panel reference is PPSSCC-432.
From 177 refused to 158 approved
Initially, the plan was bigger. It sought 177 two-storey dwellings and 303 parking spaces, plus new roads and drainage. At that point, the capital investment value was $41,700,601. The panel record shows a refusal on 28 September 2023. By then the developer had already appealed against a deemed refusal. After that, the parties settled at a conciliation conference. As a result, the court approved 158 two-storey dwellings with 280 car spaces. The case is Universal Property Group Pty Ltd v Blacktown City Council [2024] NSWLEC 1728. Because it was a settlement, the court didn’t run a full merit hearing.
The 2026 change and what’s next
Next, the developer asked to change a condition about private road widths. The panel approved that modification, MOD-25-00016 (PPSSCC-648), on 7 July 2026, after the developer lodged it in January 2025. So the consent is now settled. Still, we couldn’t find a construction start date or a builder’s name in public records. Also, the developer of an earlier 191-dwelling plan for 1584 Windsor Road (SPP-18-01551) withdrew it. So this site has been in play since 2018.
PROJECT 3 — 69 lots in a staged subdivision at 238 Commercial Road
Status: Approved (Hawkesbury City Council, DA0552/19); modification MOD0062/26 lodged in 2026
Location: 238 Commercial Road, Vineyard NSW 2765. In fact, this is one of the larger subdivisions in the Stage 1 area. Development consent DA0552/19 covers a concept subdivision and the first stage. That stage covers demolition, earthworks, roads and services in 3 sub-stages. In total, it creates 69 Torrens title lots and 3 residue lots.
Then in 2026, the owner lodged a section 4.55(2) modification, MOD0062/26. It seeks 1 more lot in Stage 3 and also revises Stage 5 by adding a Stage 6. In other words, the estate is still being fine-tuned 7 years after the first application. However, the public listing doesn’t give the original approval date or the developer’s name. We also found no decision on the modification yet. So the next step is the council’s call on MOD0062/26.
PROJECT 4 — 29 lots at 260 Commercial Road
Status: Deferred commencement consent granted (Hawkesbury City Council, DA0199/25); MOD0026/26 seeks to make it an active consent
Location: 260 Commercial Road, Vineyard NSW 2765, a short way along from Project 3. DA0199/25 is a subdivision of 29 residential lots and 2 residue lots. It also includes earthworks, new roads, drainage, utilities and street trees. Because it’s integrated development, the Rural Fire Service and the water regulator also had a say.
Initially, the council issued a deferred commencement consent. In other words, the approval only becomes active once the owner satisfies set matters. Now, a section 4.55(1) modification (MOD0026/26) asks to turn it into an active consent. Those matters would then sit in an ordinary condition instead. So if the council agrees, civil works could start sooner. We couldn’t find a determination on the modification yet, so watch the council tracker for it.
PROJECT 5 — 15 lots at 283 Commercial Road
Status: Lodged with Hawkesbury City Council; no public decision found
Location: 283 Commercial Road, Vineyard NSW 2765, on the odd-numbered side of Commercial Road. The application seeks 15 residential lots and 2 residue lots. It also covers demolition, civil works, landscaping, retaining walls and utilities. Like 260 Commercial Road, it’s integrated development under the Water Management Act and the Rural Fires Act.
For this one, the public listing gave us no DA number or lodgement date. We also found no decision, so treat it as lodged rather than approved. Still, it shows how Stage 1 fills in: one rural block at a time, each turning into 10 to 70 lots.
Smaller Vineyard development applications in 2026
Of course, not every application gets through. For example, DA0365/26 sought to split 52 Chapman Road into 3 lots. But the council listing shows it as returned. Still, single dwelling applications keep coming, such as DA0348/26 for a 2-storey house at 18A Boundary Road. These won’t change the suburb alone, but together they show where the build-out is up to.
PROJECT 6 — Depot and warehouse uses at 172 Commercial Road
Status: LEP amendment approved and published 6 December 2024 (PP-2023-1373); development application still to come
Location: 172 Commercial Road, Vineyard NSW 2765, on the corner of Commercial Road and Chapman Road. Currently, the site is about 4.8 hectares over 2 lots. It’s in Stage 2 of the precinct, directly across Chapman Road from the rezoned Stage 1 housing. Initially, Mecone prepared the planning proposal for the landowner.
What the planning proposal changed
The land already holds a depot, 3 warehouses and outdoor storage. They run under existing use rights, since the zoning banned those uses in 1984. So the owner asked to add “depot”, “light industry” and “warehouse or distribution centre” as additional permitted uses. However, the RU4 rural zoning stays the same. The Planning Portal record shows a gateway approval on 20 March 2024. Next, exhibition ran from 12 June to 10 July 2024. Then the state published the amendment on 6 December 2024.
The exhibited version capped floor space for these uses at 8,000 m². That includes a possible new 5,500 m² storage building. It also set 28 February 2027 as the date for lodging a development application. We haven’t found that DA yet, so that’s the date to watch. For neighbours, the trade-off is likely more trucks on Commercial Road in exchange for a tidier, controlled site.
PROJECT 7 — The Vineyard Precinct Stage 2 rezoning, still deferred
Status: Deferred by the NSW Government; no rezoning timeframe
Location: the balance of the precinct outside Stage 1, including land around Chapman Road, Vineyard NSW 2765. The state’s line hasn’t changed in years. Its precinct page still says the Stage 2 rezoning will wait for confirmation of essential services. In fact, the 2017 finalisation report gives 2 reasons. First, there was no timeframe for water, sewer and power. Second, the land sits inside the study area for the Outer Sydney Orbital, a future motorway and freight corridor.
As for future use, the North West land use plan flags Stage 2 as possible employment land, not housing. Also, the 172 Commercial Road report repeats that Stage 2 has no rezoning timeframe. So if you own rural land in Stage 2, the realistic outlook is a long wait. The next step is the state confirming servicing, and it hasn’t set a date.
The Infrastructure Behind the Growth
Roads matter most here, because Vineyard is a car suburb. In fact, a March 2025 ministerial release said the level crossing closes up to 5 times an hour. So here’s what has money and what doesn’t.

Bandon Road: $400 million and the level crossing removal
Above all, this is the big one for Vineyard development. The Bandon Road Corridor Upgrade and Extension would turn Bandon Road into a 6.5 km, 4-lane divided road. It would then run from Windsor Road at Vineyard to Richmond Road at Marsden Park. It also includes a road underpass beneath the Richmond line, which removes the level crossing. On top of that, a new pedestrian bridge would link Wallace Road to Riverstone Parade for station access.

Initially, the Albanese and Minns governments split $150 million for planning and early works. Then on 19 July 2026, the state added $250 million for the priority eastern section. That’s a 2.5 km stretch from Windsor Road to Vineyard station. So the state’s share is now $325 million, plus $75 million from Canberra. At the time, the release said work would “commence at the end of the year”. However, the project page now says construction is “expected to commence by September 2027”. We’d plan around the later date.
Early works and a new car park at Vineyard station
Right now, early works are already happening near Vineyard station. Transport awarded the contract in March 2026, and work began on 28 April 2026 at the Riverstone Parade intersection. It includes a commuter car park with more than 70 spaces, for example. There’s also accessible parking, better bus stops and about 150 metres of new footpath. Now the project page says this safety work should finish by the end of 2026.

Windsor Road, Boundary Road and the station
Windsor Road through Vineyard became 4 lanes in 2006 and 2007, so no new Vineyard section is planned. Further south, though, the 2 governments have committed a joint $400 million to the Windsor Road upgrade at Rouse Hill, between Mile End Road and Commercial Road. It’s still in early design, with no construction date. Locally, the council contributions plan includes a Boundary Road upgrade at about $32.3 million. Of that, 43% falls on Vineyard developers, while other precincts pay the rest. As for the station, an old idea to move it south never got funding, so it stays put.

Schools for Vineyard families
Currently, Vineyard Public School is preparing to move. According to a 13 November 2025 release, its students and staff will move to a new public school in Grantham Farm. The site is at the corner of Crown and Hamilton streets. That school will take 500 students in 27 permanent classrooms. Also, a co-located preschool will cater for 120 children a week. Builders were due to start in late 2026, ahead of opening on Day 1 Term 1 2028. School Infrastructure NSW ties the move to the future Bandon Road upgrade.

Separately, the Stage 1 plan reserves a 2.8 hectare site for a proposed primary school near the village centre. But we couldn’t find a funded project for it, so treat it as land on a plan for now.

Parks, water and power in the Vineyard development
In addition, the contributions plan carries $165.9 million of local infrastructure in June 2020 dollars. That covers, for example, 9 parks along the Killarney Chain of Ponds, playing fields, stormwater basins and collector roads. For services, the state says part of Stage 1 already has water, sewer and power for about 500 homes. Also, Endeavour Energy is to build a substation for the rest. In the meantime, developers may have to fund their own lead-in sewer mains. That’s one reason lots come out in small batches.
What’s Next to Watch in Vineyard Development
Here are the milestones we’ll be tracking over the next 18 months.
- The station car park and Riverstone Parade safety works are due to finish by the end of 2026. So commuters should soon have more than 70 new spaces.
- Watch for the main construction contract on the Bandon Road eastern section, with work expected to start by September 2027.
- Next, builders were due to start on the Grantham Farm school in late 2026. It opens in Term 1 2028 for Vineyard Public School families.
- The next step at 238 and 260 Commercial Road is a council decision on 2 modifications. Those would free up more lots.
- Then watch for a development application at 172 Commercial Road by 28 February 2027.
- Look out for a building start on the 158 Windsor Road townhouses, since the panel has now cleared the road width change.
- Stage 2 is the long game. Watch for a servicing plan and a firm Outer Sydney Orbital route, because neither has a date yet.
Vineyard Development: Project Status and Delivery Timing
| Project | Homes | Stage | Decision maker | Expected timing |
|---|---|---|---|---|
| Stage 1 rezoning | Up to 2,300 | Currently building out | NSW Government | Ongoing; no end date yet |
| 1578 to 1586 Windsor Road | 158 | Approved; mod approved Jul 2026 | Land and Environment Court; Central City panel | Start not announced yet |
| 238 Commercial Road | 69 lots plus 1 proposed | Approved; mod now lodged | Hawkesbury City Council | Staged; mod decision still pending |
| 260 Commercial Road | 29 lots | Deferred commencement; mod now lodged | Hawkesbury City Council | Mod decision still pending |
| 283 Commercial Road | 15 lots | Lodged, still under assessment | Hawkesbury City Council | Not stated yet |
| 172 Commercial Road | None, because it’s employment use | LEP change published | Hawkesbury City Council | DA due by Feb 2027, then assessment |
| Stage 2 rezoning | Not proposed, since it’s likely employment land | Still deferred | NSW Government | No timeframe yet |
Our Take on Vineyard Development
Vineyard is a slow burner, but we think that’s mostly fine. The housing cap, the flood limits and the fragmented ownership mean you won’t see a wall of apartments here. Instead, it’s a steady stream of subdivisions on Commercial Road, plus 1 townhouse estate on Windsor Road. As a result, it keeps the place low-rise. But it also means the village centre and the Stage 1 school may lag the homes by years. Compare that with Box Hill across Windsor Road, where single big developers have pushed shops and schools along much faster.
In short, the real change is Bandon Road. Once the level crossing goes, Vineyard gets a 4-lane link towards Marsden Park. It also gets an easier run to the station. That’s funded for the eastern section, which is more than most growth suburbs can say. So we’d buy here for the land, the space and that road. We wouldn’t buy for Stage 2, which has no date at all. Buyers in nearby Riverstone face the same question, and the answer there is similar.
Questions Locals Are Asking About Vineyard Development
When will the Vineyard level crossing close?
There’s no closure date yet. The underpass is part of the priority eastern section of Bandon Road, which now has funding. Transport says major construction should start by September 2027, but it hasn’t published a finish date.
Which school will Vineyard kids go to?
For now, Vineyard Public School stays open on its current site. Then, once the Grantham Farm school opens, students and staff will move there. The state is targeting Term 1 2028. But the Stage 1 school site has no funding announced yet.
Is my land in Stage 2 going to be rezoned?
Not soon. The state is holding Stage 2 until essential services are in place. Also, the land sits in the Outer Sydney Orbital study area. When it does move, the current thinking is employment land rather than housing.
Is Vineyard flood-prone?
Yes, parts of it are, especially near the creeks. About a third of the precinct sits below the 1 in 100 year flood level. So no new homes can go under the flood planning level. So check the lot itself before you buy, using the tools in our guide to flood and bushfire maps. If you’re a first home buyer, also check the 5% deposit scheme price caps for this area.
This article is general information based on NSW Department of Planning, Housing and Infrastructure, NSW Planning Portal, Transport for NSW, School Infrastructure NSW, Hawkesbury City Council and Land and Environment Court records available at publication. It isn’t financial advice. Approvals, funding and timelines can change, so check current details with the council and the relevant agency before you buy.