Australian Property & Development News

Aerotropolis Core Development 2026: Every Bradfield Project and Its Status

The Aerotropolis Core carries six active development projects around Bradfield, the first new city Australia has built in a century. Approvals and lodged applications commit more than $2.3 billion of private capital.

The NSW Government approved its eighth State Significant Development across the whole 11,200-hectare Aerotropolis in July 2026. Six years of the planning framework have produced eight approvals.

Written by Daniel Whitfield, founder of Australia Develops, who has personally bought, subdivided, and built property across Australia.

Aerotropolis Core Development 2026 — The Pipeline

Six schemes hold approvals or sit in assessment inside the precinct. They range from a $1 billion residential superlot to two apartment towers on a road that still looks rural.

SiteDeveloperScaleStatus
5.7-hectare superlot, Bradfield City CentrePlenary1,400 homes, $1 billionDevelopment agreement signed
Second Building, Bradfield City CentreBradfield Development Authority7,000 m², semiconductor packagingUnder construction
475 Badgerys Creek RoadIngham Property Group184 ha, 625,000 m², 12,500 jobsMaster plan approved
475 Badgerys Creek Road, first stageALDI Foods22.1 ha, 106,706 m², $1.15 billionApproved March 2026
60 Kelvin Park DriveKK Capital211 apartments, $144 millionPrepare EIS
26 Kelvin Park DriveTaylor Smith Projects401 apartments, $80 millionScoping report lodged
Active projects inside the Aerotropolis Core precinct, July 2026.
114 ha
Bradfield City Centre
10,000
Homes the master plan allows
50,000–60,000
Jobs the precinct targets
$31 billion
Aerotropolis investment pipeline

The precinct wraps the Bradfield Metro station and the Wianamatta–South Creek corridor. The department planned it as the dense centre of the Aerotropolis, not as another warehouse belt.

That distinction drives everything in the table. Bradfield City Centre takes the housing, the research floor space and the retail, while the land east of it takes the freight.

Cargo flights began landing at Western Sydney International Airport in July 2026, and the operator has scheduled passenger services from October 2026. Every timeline in this precinct now runs against that date.

Where the Projects Sit

Where the projects sit
WESTERN SYDNEY INTERNATIONAL AIRPORT
Cargo from July 2026 · passenger services from October 2026
BRADFIELD METRO STATION & CENTRAL PARK
Two-hectare park · SSD-65490715 approved March 2025
FIRST AND SECOND BUILDINGS
AMRF opened 2025 · semiconductor plant under construction
PLENARY SUPERLOT
5.7 hectares · 1,400 homes · adjoins Central Park
KELVIN PARK DRIVE
Numbers 60 and 26 · 612 apartments proposed
475 BADGERYS CREEK ROAD
184 hectares · Ingham estate · ALDI on 22.1 hectares
Transport for NSW has required a realigned intersection where the planned Eastern Ring Road meets Badgerys Creek Road.

Schematic layout — relative positions only, not to scale.

Google Maps shows the streets but not the planning boundaries. For the controls applying to any individual parcel, the NSW Planning Spatial Viewer is the authoritative source.

PROJECT 1 — $1 Billion for the First 5.7 Hectares of Bradfield City Centre

STATUS: DEVELOPMENT AGREEMENT SIGNED, DECEMBER 2025

Melbourne-based Plenary signed a $1 billion development agreement with the NSW Government in December 2025. The deal covers the first 5.7-hectare superlot released inside Bradfield City Centre.

Plenary will build 1,400 homes on the site, with 10 per cent set aside as affordable housing. The company works from Toronto, Los Angeles, Singapore, London and Dubai.

Graded development lots in the Aerotropolis Core at Bradfield City Centre with new kerbed roads and street lighting installed before construction
New roads and street lighting reach the graded lots at Bradfield City Centre ahead of any building.

A quarter of the site permits other uses. Those include a hotel, advanced industries, a university campus, retail, childcare and health facilities, and a 1,500-square-metre hospitality venue overlooking Central Park.

The site adjoins the First Building, which holds the Advanced Manufacturing Readiness Facility hall, along with the two-hectare Central Park and the Metro station.

Plenary said it would seek a university partner and a major commercial anchor tenant during 2026. It has named neither, and that gap matters more than the headline number.

The company also plans a State Significant Development application for the restaurant and a concept plan covering housing, a hotel and commercial space on the northern part of the site.

Plenary acts as long-term development partner alongside the Bradfield Development Authority. Its earlier work includes the $5 billion La Trobe University city plan and the $294 million Geelong Convention Centre.

The company has committed to delivering the first stage within five years. Later stages carry no published date.

PROJECT 2 — Australia’s First Semiconductor Packaging Plant, on 7,000 Square Metres

STATUS: APPROVED APRIL 2025, UNDER CONSTRUCTION SINCE 16 JULY 2026 — SSD-58591961

The Bradfield Development Authority broke ground on the Second Building on 16 July 2026. Deputy Premier Prue Car and Planning Minister Paul Scully turned the first soil.

Hansen Yuncken holds the head contract and will deliver the building across 2026 and 2027. It rises beside the First Building at 215 Badgerys Creek Road.

The Western Parkland City Authority lodged the application in May 2024 and won approval in April 2025 as SSD-58591961. Architectus designed the five-storey building.

Two floor areas circulate for it. The ministerial release describes a purpose-designed 7,000 square metres, while the consent records 10,847 square metres across five storeys on a 5,997-square-metre site.

The building will house Australia’s first commercial Semiconductor Advanced Packaging Facility. About 13 such facilities operate anywhere in the world.

Advanced manufacturing research building under construction in Western Sydney with steel frame, partial cladding and a tower crane
Hansen Yuncken is building the Second Building beside the First, across 2026 and 2027.

ISO 5 cleanroom laboratories will support advanced microscopy, electronics, taping and dicing. The government expects the plant to serve quantum computing, photonics, sensing, communications and medical technology.

A second advanced manufacturing hall will expand the AMRF, which opened in 2025. Commercial office and collaboration space fills the rest of the building.

The design carries a biosolar green roof, a 5-Star Green Star target and open space linking the two buildings.

One figure needs care. The ministerial release counts $300 million across both buildings, while several trade reports described the Second Building alone as a $300 million facility.

PROJECT 3 — 184 Hectares and 625,000 Square Metres at 475 Badgerys Creek Road

STATUS: MASTER PLAN APPROVED 11 JULY 2025 — WSA_MP01

The Minister for Planning and Public Spaces approved the IPG Badgerys Creek Road Master Plan on 11 July 2025. No private master plan had reached approval anywhere in the Aerotropolis before it.

Ingham Property Group owns the land at 475 Badgerys Creek Road. The Ingham family has held it since the 1960s, which is why a single plan covers so much ground.

The department describes a 184-hectare development hub. Ingham’s own portfolio page lists 182.4 hectares as approved and operational, so the two figures differ slightly.

The plan guides 625,000 square metres of mixed-use gross floor area and nearly 12,500 jobs across 25 lots for enterprise, commercial and retail use.

Cleared Aerotropolis Core enterprise estate site on Badgerys Creek Road with survey pegs, silt fencing and earthmoving machinery
Earthworks open the 184-hectare Ingham estate on Badgerys Creek Road.

More than 45 hectares go to open space and landscaped areas, roughly twice the area of Barangaroo. Three riparian corridors run through that open space.

Approval also changed the planning rules themselves. The master plan amended State Environmental Planning Policy (Precincts — Western Parkland City) 2021 and the Western Sydney Aerotropolis Precinct Plan.

Transport for NSW required changes to the future intersection of Badgerys Creek Road and the planned Eastern Ring Road. The department warned these “may involve increased property acquisitions”, pending detailed planning.

Anyone holding land near that intersection should read the final plan rather than the exhibited version. The department exhibited the draft from 15 November to 13 December 2024.

Twenty-three submissions came back: 15 from government agencies and 8 from residents or landowners. Submissions changed the road network design and the open space configuration.

PROJECT 4 — ALDI’s $1.15 Billion Automated Warehouse on 22.1 Hectares

STATUS: APPROVED 9 MARCH 2026 — SSD-76913969

ALDI Foods won approval for SSD-76913969 in March 2026. It became the first State Significant Development approved inside the Ingham master plan area.

The warehouse occupies 22.1 hectares of the estate’s first stage. Approved gross floor area reaches 106,706 square metres, the largest distribution centre consented in the Aerotropolis so far.

The consent covers a 103,546-square-metre warehouse with ambient, chilled and freezer zones, a 2,813-square-metre office, a gatehouse and a truck wash. SBA Architects designed the building.

Automated distribution warehouse under construction with precast concrete tilt panels and a mobile crane in Western Sydney
Tilt panels rise on the warehouse floor plate, which the consent sets at 106,706 square metres.

Heights run from 22.8 metres to 42 metres. The facility will operate 24 hours a day, seven days a week, and about 80 per cent of internal processes will run unmanned.

Construction should generate 3,728 jobs, and the completed centre will employ 585 people. It will supply ALDI’s 200-store network across New South Wales.

ALDI has included rooftop solar and targets net-zero operations by 2035. The retailer described the project as a base for expanding its store network.

Two figures circulate for this warehouse. Trade coverage reported 87,000 square metres and $1 billion, while the application documents record 106,706 square metres and $1.15 billion.

PROJECT 5 — 211 Apartments and Eight Buildings at 60 Kelvin Park Drive

STATUS: PREPARE EIS — SSD-74765211

KK Capital Pty Ltd wants to replace a single house at 60 Kelvin Park Drive with eight residential buildings. Jomon Varghese, Kiran Tippani and Konda Reddy Bhupesh Valipreddy lead the company.

The $144 million scheme covers a two-hectare site zoned MU — Mixed Use. It proposes 211 apartments, ground floor retail and commercial space, 760 car parking spaces and two childcare facilities.

Rural-residential street on Kelvin Park Drive with wide verges, post and wire fencing and single-storey houses on large lots
Rural-residential blocks still line Kelvin Park Drive, where two schemes propose 612 apartments.

The buildings reach up to 12 storeys, and the proposal subdivides the site into two lots. Urbis prepared the scoping report.

Urbis argued that the existing single dwelling “is not in alignment with its zoning and development potential”. That sentence explains most of what is happening on this road.

The Major Projects register lists the application at Prepare EIS stage, inside the Liverpool City local government area, with 27 pieces of agency advice on file.

PROJECT 6 — 401 Apartments at 26 Kelvin Park Drive

STATUS: SCOPING REPORT WITH THE DEPARTMENT

Taylor Smith Projects lodged a scoping report in February 2024 for 26 Kelvin Park Drive. The $80 million scheme sits on a two-hectare block.

The proposal places 401 apartments in four blocks running from 8 to 16 storeys, over podiums of three to four storeys. IDA Design Group and Architecture AND prepared the concept.

Floor space splits into 5,150 square metres of office, a 3,150-square-metre retail podium, a 2,000-square-metre supermarket and a 500-square-metre childcare centre.

The developer requested Secretary’s Environmental Assessment Requirements, the step that precedes a formal development application. No determination had followed by mid-2026.

Read the two Kelvin Park Drive schemes together and the picture sharpens. Two adjoining two-hectare blocks carry 612 proposed apartments on a road that still holds rural-residential houses.

Eight Approvals in Six Years

The Aerotropolis planning framework commenced on 1 October 2020 and covers 11,200 hectares. Burrah Park, approved in July 2026, became the eighth State Significant Development approved anywhere inside it.

That works out to roughly one state significant approval every nine months. Meanwhile the government cites a $31 billion investment pipeline and a contribution towards 200,000 new jobs in the Western Parkland City.

How the precinct reached this point
1 Oct 2020
The Aerotropolis planning framework commences across 11,200 hectares
4 Sep 2024
The Minister approves the Bradfield City Centre Master Plan
15 Nov – 13 Dec 2024
The department exhibits the IPG master plan and receives 23 submissions
6 Mar 2025
Central Park wins approval as SSD-65490715
2025
The AMRF opens inside the First Building
11 Jul 2025
The Minister approves the IPG Badgerys Creek Road Master Plan
Dec 2025
Plenary signs the $1 billion development agreement for the first superlot
9 Mar 2026
ALDI wins approval as SSD-76913969
16 Jul 2026
Hansen Yuncken breaks ground on the Second Building

The gap is not a contradiction, and the timeline shows why. Master plans and precinct rules had to land first, and most of them arrived only in 2024 and 2025.

The practical lesson sits in which document a number comes from. A precinct target describes capacity, while a consent describes a building someone must now fund and construct.

The Aerotropolis Core Jobs Target and What Documents Carry

The department targets 50,000 to 60,000 jobs for the Aerotropolis Core, on its precinct planning page. Two approved master plans and one consent already account for a large share of the lower figure.

SourceJobsDocument
Bradfield City Centre Master Plan20,000Approved 4 September 2024
IPG Badgerys Creek Road Master Plan12,500Approved 11 July 2025
ALDI distribution centre585 permanentSSD-76913969, approved March 2026
Accounted for in approved documentsAbout 33,000—
Jobs recorded in approved Aerotropolis Core documents, against a precinct target of 50,000 to 60,000.

Roughly 33,000 of the low-end target therefore sits inside documents that carry a date and a decision maker. The balance depends on land that holds no master plan yet.

One caveat matters. The master plan figures describe full build-out over decades, while ALDI’s 585 counts permanent staff at one completed warehouse, so the numbers do not compare like for like.

The Land Still on the Market

Several mixed-use blocks on Kelvin Park Drive remain unsold. Agents market them on development potential rather than on any approval, much as they do across nearby Bringelly.

Colliers advertises 126 Kelvin Park Drive as a high-rise mixed-use site with potential for 421 residential units and 11,950 square metres of commercial space.

Bradfield International Real Estate lists 16 Kelvin Park Drive as 2.01 hectares zoned MU with no development approval, and an existing house providing income during the approvals process.

Those figures come from marketing material, not from a consent. Anyone pricing such a site should confirm the controls independently before treating a yield claim as an entitlement.

How to Check a Specific Site Here

Start with the NSW Planning Spatial Viewer for the zone, height and floor space ratio applying to the parcel, then read the Western Sydney Aerotropolis Precinct Plan for the precinct-specific controls.

Search the Major Projects register for anything state significant on or near the block, and check Liverpool City Council for local applications.

The Infrastructure Behind the Aerotropolis Core Pipeline

The master plan places all 114 hectares of the city centre within 400 metres of the Bradfield Metro station. That single constraint shapes every height and density decision in the precinct.

Central Park won approval as SSD-65490715 on 6 March 2025, with Modification 1 determined on 2 May 2025. ASPECT Studios won the design competition with a scheme drawing on Dharug cultural heritage and Sky Country.

The First Building already operates, housing the Advanced Manufacturing Readiness Facility that opened in 2025. The Second Building rises beside it.

Enabling works have delivered 4 kilometres of new roads, 8 kilometres of active transport links and 178 on-street car parking spaces. Reporting in early 2026 put roughly a third of Bradfield at development-ready.

The M12 motorway and the metro line carry the precinct’s external connections, while planned Elizabeth Drive upgrades serve the freight estates to the north.

The airport project and the suburbs around it, covered on the Australia Develops channel.

What Has Not Been Confirmed

Five things in this precinct carry a date and a decision maker. Five others do not, and the difference is worth keeping straight.

On the record
Bradfield master plan, approved 4 September 2024
IPG master plan, approved 11 July 2025
ALDI consent SSD-76913969, March 2026
Central Park consent SSD-65490715, March 2025
Plenary’s $1 billion development agreement
Not settled
Plenary’s university partner and anchor tenant
Determination dates for both Kelvin Park Drive schemes
ALDI’s floor area, reported two ways
The Ingham estate area, 184 or 182.4 hectares
Which parcels the realigned intersection takes

ALDI’s warehouse appears as 87,000 square metres in trade coverage and 106,706 square metres in the consent documents. Use the consent figure.

The Ingham estate appears as 184 hectares in the department’s approval and 182.4 hectares on the owner’s own portfolio page. Both remain current, and neither is wrong.

Neither Kelvin Park Drive application carries a determination date. The Taylor Smith scoping report has now waited more than two years without a decision.

Transport for NSW’s intersection realignment may require further land acquisition, but the department has not published which parcels it affects.

Project Status and Delivery Timing

ProjectScaleValueStageDecided by
Plenary superlot, Bradfield City Centre1,400 homes on 5.7 ha$1 billionDevelopment agreement signedNSW Government
Second Building7,000 m² semiconductor and AMRF hall$300m across both buildingsUnder constructionBradfield Development Authority
IPG Badgerys Creek Road estate184 ha, 625,000 m², 25 lotsNot publishedMaster plan approvedMinister for Planning
ALDI distribution centre22.1 ha, 106,706 m²$1.15 billionApproved March 2026Department of Planning
60 Kelvin Park Drive211 apartments, 8 buildings$144 millionPrepare EISDepartment of Planning
26 Kelvin Park Drive401 apartments, 4 blocks$80 millionScoping reportDepartment of Planning
Status of Aerotropolis Core projects as recorded in planning documents, July 2026.

Summary

The Aerotropolis Core now runs on documents rather than announcements. Two master plans, three consents and one development agreement set what can be built and who decides.

Housing concentrates in Bradfield City Centre and on Kelvin Park Drive, while the enterprise floor space concentrates on the Ingham estate east of it. That split explains the whole precinct.

The nearby Northern Gateway and Agribusiness precincts took freight and industry first, and Mamre Road did the same. Bradfield is the only part of the Aerotropolis planned to hold a city.

Anyone tracking a specific block should watch two things: the determination of the Kelvin Park Drive applications, and the parcels the realigned Eastern Ring Road intersection takes.

What is the Aerotropolis Core precinct?

The Aerotropolis Core is the dense urban precinct planned around the Bradfield Metro station and the Wianamatta–South Creek corridor. The department targets 50,000 to 60,000 jobs there.

Is Bradfield the same thing as the Aerotropolis Core?

No. Bradfield City Centre covers 114 hectares inside the wider Aerotropolis Core precinct. Bradfield is also a gazetted suburb, carved from Bringelly and Badgerys Creek.

Can you build apartments in the Aerotropolis Core?

Yes, on land zoned MU — Mixed Use and outside the worst aircraft noise. Two schemes on Kelvin Park Drive propose 612 apartments between them.

How many projects have won approval in the Aerotropolis?

Burrah Park became the eighth State Significant Development approved anywhere in the 11,200-hectare Aerotropolis when the department determined it in July 2026.

This article is general information only and is not financial, legal or planning advice. See the Disclaimer for details.